Barkham Solar Farm now has a full grid connection date of 30 September 2027 under a new SSEN deal. In January the council feared waiting until 2031 or later.

Barkham Solar Farm is now due to connect fully to the electricity grid on 30 September 2027. Wokingham Borough Council has signed a new grid connection agreement with Scottish and Southern Electricity Networks (SSEN).

The council gave the date on its Barkham Solar Farm project page, which it updated on Tuesday 17 November. The page says the date covers “both the distribution and transmission elements of the connection”.

Overview

  • New connection date: 30 September 2027, for the whole connection.
  • What it replaces: in January the council said full connection had slipped to “some time between 2031 and 2035”.
  • On site now: Equans is setting up the site entrance and construction compound off Barkham Ride.
  • Panels go in: the main construction programme begins in 2027.

Why the date matters

In January the council paused the project. Changes to national grid connection rules had left it with an early connection in 2027, but full connection pushed back to between 2031 and 2035. The council said it would not sign a multi-million-pound contract without more certainty (Wokingham Borough Council, 8 January).

It signed with Equans in September anyway, saying the farm would “go live next year” (Wokingham Borough Council, 21 September). That announcement did not say whether the 2031 to 2035 problem had been solved, as we reported at the time.

The project page now answers that. It says the new agreement “resolves previous uncertainty around the connection date and the transmission constraint that affected the project during 2026”.

The date still comes with a condition. The council says the farm is expected to connect in autumn 2027 “subject to the construction and connection programmes progressing as planned”.

What is being built

The project page lists:

  • about 43,000 solar panels on council farmland north of California Country Park
  • security fencing, sensor-controlled lighting and CCTV around the edge
  • a new greenway through the site, with a signalised crossing on Barkham Ride
  • 2.66 hectares of new woodland on the southern edge

The council estimates the farm could generate more than 29 megawatts. It puts the output at about 28.6 million kWh a year, which it says would cover the electricity use of more than 10,500 homes on Ofgem’s figures. In September the council said the farm would make a surplus of more than £1 million a year after borrowing costs.

What it means for you

  • If you use Barkham Ride: the council says people “will start to see increased activity on the site” as the entrance and compound go in.
  • If you drive through Barkham or Arborfield: SSEN will lay underground cables along Edneys Hill and up Blagrove Lane to the substation on Barkham Road, opposite Ye Olde Leathern Bottle. That means works in the carriageway and traffic management. No dates have been published yet; the council says it will give “advance information about works that may affect local roads and journeys”.